COST-TO-COMPLETE ANALYSIS

Frequency:

Date of This Analysis:

Analysis completed by:

Project ID

(2)

Proposal

Price + Change Orders

($$)

(3)

Total Builder Margin

($$)

(4)

Construction Costs

($$)

(col 2)-(col 3)

(5)

Total Deposits to Date

($$)

(6)

Construction Cost to Complete Project

($$)

(7)

Remaining to be billed

($$)

(col 2)-(col 5)

(8)

Allocated to Client in Client Deposits Account

($$)

(9)

Builder Project Position

($$)

(col 6)-(col 7)-(col 8)

Totals

File Management

Project contract price +/- all project change orders.

Use Overhead and Profit calculations from estimate and change orders.

Includes direct project-related costs only. Does not include Overhead or Profit .

The sum of all payments made by Client for this project.

Sum of balances of all line items on estimate which have not been completed.

Remaining funds available on the project.

Total should equal total of Customer Deposits on Balance Sheet.

A negative number indicates a shortage of funds to complete the project.